How a park is built
Six phases lead from the first look at the parcel to day-to-day operation. We follow the Swiss SIA 112 standard so that every decision has its place. The plan grows as you read.
Plan statusPhase 1Strategic planning
Phase 1: Strategic planning
Need, site, approach
It starts with one question: what should the storage system do, and where can it stand? We record your goal, look at the parcel and check what is possible there: zoning, area, access and distance to the grid.
What we do
- Record the need and the goal
- Check site and parcel
- Size the system roughly
- Run a first business case
What you receive
An assessment of whether the site is suitable, with a guide figure for size and effort.
On the plan: the parcel, its neighbours and the substation.
Phase 2: Preliminary studies
Project definition, feasibility
Now we find out whether the project holds up. We ask the grid operator for connection capacity, check boundary setbacks, noise and fire safety, and fix the point where the park connects to the grid.
What we do
- Prepare the grid enquiry and connection request
- Pre-check setbacks, noise and fire safety
- Compare options
- Document feasibility
What you receive
A feasibility study with options, and the grid operator’s answer.
On the plan: boundary setback, access, planned cable route and connection point.
Phase 3: Project design
Preliminary design, building project, permits
The idea becomes a building project. Every unit gets its place, and the documents go to the municipality and the canton and, where required, to the Federal Inspectorate for Heavy Current Installations. The financing model takes shape at the same time.
What we do
- Preliminary design and building project with layout
- Building application and plan approval
- Fire safety and noise assessments
- Financing model and revenue calculation
What you receive
A project ready for approval, with costs, schedule and revenue calculation.
On the plan: the fence and the footprint of every unit.
Phase 4: Tendering
Tender, comparison of offers, award
We obtain offers for storage, converters, civil works and electrical works, compare them and recommend the award. After that the bill of materials is fixed: every item has a supplier and a date.
What we do
- Prepare the tender documents
- Compare the offers
- Recommend the award
- Prepare supply and works contracts
What you receive
An award recommendation with checked offers and a binding schedule.
On the plan: the items of the bill of materials, numbered.
Phase 5: Construction
Execution, commissioning, handover
Foundations, cable route, delivery. The containers are set down, connected and tested. The grid operator accepts the connection, and the park goes on the grid.
What we do
- Detailed design and site management
- Coordinate delivery and installation
- Commissioning and tests
- Acceptance with the grid operator
What you receive
An accepted park with complete documentation.
On the plan: containers and conversion stations are in place, the cable is laid.
Phase 6: Operation
Operation, monitoring, maintenance
The park is at work. We monitor it, plan the maintenance and make sure it delivers on the market and in the grid what it was built for.
What we do
- Operation and monitoring
- Maintenance and repairs
- Marketing with partners
- Reports on yield and condition
What you receive
Regular reports and one contact person for the whole operation.
On the plan: the connection point is green, energy is flowing.
One plan, one calculation, one status
We plan with the Gridenity BESS Park Developer, our own planning tool. Site check, layout, bill of materials and revenue calculation live in one place. That keeps every figure traceable, from the first sketch to acceptance.
Which phase is your project in?
Whether you only have a plot of land or already hold a grid commitment: we join where you are.